Which of the following statements describes the difference between capacity requirements
planning and material requirements planning ?
A.
Material requirements planning ignores capacity constraints.
B.
Capacity requirements planning accounts for material.
C.
Material requirements planning is confined by capacity constraints.
D.
Capacity requirements planning only accounts for critical resources.
Correct answer is A