What is the order point when demand is 120 units per week, the lead time is 2 weeks, and safety stock is 60

What is the order point when demand is 120 units per week, the lead time is 2 weeks, and

safety stock is 60 units?

PrepAway - Latest Free Exam Questions & Answers

A.
360

B.
180

C.
240

D.
300