Forecasts, requested changes, recommended corrective actions, and organizational process asset updates are all outputs of which process?

A.
Risk response planning

B.
Risk monitoring and controlling

C.
Performance reporting

D.
Manage stakeholders

Explanation:
Performance Reporting is:
The process of gathering and communicating information regarding the current status of a project as well as projections for progress over time.
Durng performance reporting:

Information regarding the work being accomplished
resources being used is collected, analysed and displayed in various report formats.