Which knowledge area is concerned with the process required to ensure timely and appropriate generat

Which knowledge area is concerned with the process required to ensure timely and appropriate generation, collection, distribution, storage, retrieval, and ultimate disposition of project information?

A.
Project integration management

B.
Project communications management

C.
Project Information Management System (PIMS)

D.
Project scope Management