PMI Exam Questions

Which of the following is NOT an output of the control schedule process?

Which of the following is NOT an output of the control schedule process?

A.
Organizational process assets

B.
Change requests

C.
Project termination request

D.
Project document updates

Explanation:
The project termination request is not an output of the control schedule. Early termination of a
project is a closing process and usually does not stem from the project manager. The outputs of

the control schedule process are as follows: Work Performance Measurements: The work
packages and control accounts are documented and communicated to the stakeholders.
Organizational Process Assets Updates: The assets that are updated are: corrective actions
chosen and the reasons, causes of variance, and other types of lessons learned from project
schedule control. Change Requests: It is processed for reviews and disposition through the
Perform Integrated Change Control process. Project Management Plan Updates: The elements
that need to be updated are: schedule baseline, schedule management plan, cost baseline.
Project Document Updates: The elements that need to be updated in project document updates
are: schedule data and project schedule.