Analogous estimating ___________. seenagape 8 years ago Analogous estimating ___________. A.Uses bottom-up estimating techniques. B.Uses the actual costs from a previous, similar project C.Is synonymous with top-down estimating D.Both B and c ← Previous question Next question →