Which of the following activity is not performed as part of the direct and manage project execution

Which of the following activity is not performed as part of the direct and manage project execution process?

A.
Monitor implementation of approved changes

B.
Validate deliverables

C.
Staff, train, and manage the project team

D.
Manage cisks and implement risk responses

Explanation:
In the direct and manage project execution process, approved changes are implemented but monitoring of those changes is part of monitoring OR controlling project work.