The contract must have ________.

You are the project manager and you have created a contract for your customer. The contract must have ________.

A.
Offer and consideration

B.
Start date and acceptance of start date

C.
Signatures and the stamp of a notary public

D.
Signatures of all stakeholders

Explanation:
A contract must have Offer and consideration. Not all contracts demand signatures and notary public involvement. Contract may specify a start date, but the Acceptance of the start date is not needed for all contracts.