When a blade is inserted into a bay that has a VCM profile assigned, which action will the VCM
perform before the server is allowed to power on?

PrepAway - Latest Free Exam Questions & Answers

A.
Determine the Server OS

B.
Download new firmware update

C.
Configure the NIC ports with profile provided MAC addresses

D.
Check the embedded teaming configuration

Explanation: