An implementation plan should include an agreed-on time for the final rollback decision. What
should this decision be scheduled?

PrepAway - Latest Free Exam Questions & Answers

A.
After the cutover to the new solution and the first set of validation tests and just before the user
acceptance tests (UATs)

B.
after the first steps of the rollback plan have been implemented, about ten minutes before the
end of the maintenance window

C.
just before the point of no return, which is calculated by subtracting the rollback time from the
end of the maintenance window

D.
ten minutes before the end of the maintenance window or one hour into the implementation,
whichever occur first