What is the preferred time for completing racking and labeling of equipment for a new implementation?

What is the preferred time for completing racking and labeling of equipment for a new
implementation?

PrepAway - Latest Free Exam Questions & Answers

A.
After the scheduled outage has begun and initial tests have indicated success

B.
Before the scheduled outage

C.
At any time between the beginning of the scheduled outage and the point of no return

D.
At the beginning of the scheduled outage