What change can the administrator make to correct the problem?
— Exhibit –
— Exhibit —
Refer to the Exhibit.
An administrator is seeing a warning on one of their hosts. The warning in the Triggered Alarms
panel appears to come from a custom configured host alarm. The administrator has not seen any
actions taken for this alarm even though the actions are configured in the alarm definition. The
configured actions are shown in the exhibit.
What change can the administrator make to correct the problem?
Which change will eliminate the symptom in the performance chart shown in the exhibit?
What differentiates a private cloud from a vSphere Infrastructure?
What differentiates a private cloud from a vSphere Infrastructure?
Which component is the metering tool for vCloud administration?
Which component is the metering tool for vCloud administration?
What is the default VFAT scratch partition size for ESXi 5.x when installed on a USB drive?
What is the default VFAT scratch partition size for ESXi 5.x when installed on a USB drive?
Which collector is configured incorrectly?
An administrator is unable to find network traffic details while running vCloud hierarchy reports.
The network administrator confirms that there was network traffic during the report time span.
Which collector is configured incorrectly?
Why did this occur?
An administrator has scheduled a report to run at 8 PM nightly and has configured a number of
recipients to receive the report. After the report runs, the administrator discovers that a link to the
report was sent to the recipients, not the report itself.
Why did this occur?
Which report type does the user need?
In a large organization, a user has 10 VMs deployed in vCloud Director, backed by a Pay-As-YouGo allocation model. The user needs to determine the charges being incurred for resource usage.
Which report type does the user need?
What is a possible reason for the error?
An administrator attempts to delete the network named Internet but receives an error.
What is a possible reason for the error?
How can an administrator provide greater capacity for creating additional Organizational Networks?
An existing port group-backed network pool has been fully provisioned (25 out of 25 networks
have been deployed).
How can an administrator provide greater capacity for creating additional Organizational
Networks?