PrepAway - Latest Free Exam Questions & Answers

Category: VCP5-DCV (v.1)

Exam VCP5-DCV: VMware Certified Professional – Data center Virtualization (on vSphere 5) (update August 10th, 2014)

Which task would successfully resolve this problem?

Refer to the Exhibit.

An administrator has deployed a two-node cluster with HA and DRS enabled. DRS has been

configured for fully automated mode. The management and vMotion interfaces have been
configured on separate physical networks. Initial DRS testing on this cluster reveals that virtual
machines are not being migrated despite great disparity in resource use between the ESX hosts in
the cluster. The exhibit shows the error and the network configuration for one of the hosts.
Which task would successfully resolve this problem?

Which two options could be part of the plan to resolve the issue while minimizing the amount of resources rese

Two child resource pools exist for a DRS cluster.
The Production resource pool has been configured with a CPU reservation of 20GHz and a
memory reservation of 20GB. The pool has 16 single-processor virtual machines and 4 dualprocessor virtual machines. Each of these virtual machines has a CPU reservation of 1GHz and a
memory reservation of 1GB.
The Development resource pool and it’s virtual machines have been configured with no
reservations. The pool has 1 single-processor virtual machine and 1 dual-processor virtual
machine. CPU Shares are set to 4000 and Memory Shares are set to 163840.
The Production team members occasionally complain about the performance of their servers.
Which two options could be part of the plan to resolve the issue while minimizing the amount of
resources reserved by the pool? (Choose two.)

What happens if an ESXi 5.x host that is running the vCenter Server virtual machine experiences a power outage

vCenter Server is running in a virtual machine that is part of a vSphere DRS cluster. The vCenter
Server virtual machine has been tested and can successfully migrate with vMotion between all
ESXi hosts in the cluster. DRS is configured for partial automation.
What happens if an ESXi 5.x host that is running the vCenter Server virtual machine experiences
a power outage?


Page 24 of 58« First...10...2223242526...304050...Last »