The administrator wants to power on VM-K2, which has a 2GHz CPU reservation. VM-M1, VM-M2, and VM-K1 are all p

The administrator wants to power on VM-K2, which has a 2GHz CPU reservation. VM-M1, VM-M2, and VM-K1 are all powered on. VM-K2 is not powered on.

The exhibit shows the parent and child resource reservations.

If Resource Pool RP-KID is configured with an

expandable reservation, which statement is true?

A. VM-K2 will be unable to power on because there are insufficient resources.

B. VM-K2 will be able to power on since resource pool RP-KID has 2GHz available.

C. VM-K2 will be unable to power on because only 2GHz are reserved for RP-KID.

D. VM-K2 will receive resource priority and will be able to power on this scenario.