Which one of the following best describes the purpose of ADM Phase E?

A.
To define the initial implementation plans
B.
To define the scope, identifying stakeholders and obtaining approvals
C.
To develop the Technology Architecture
D.
To manage requirements throughout the ADM
E.
To perform architectural oversight for the implementation
TOGAF 9.1 book, section 13.2 – Phase E is the initial step on the creation of the Implementation and Migration Plan which is completed in Phase F. It provides the basis of a well considered Implementation and Migration Plan that is integrated into the enterprise’s portfolio in Phase F.
The answer is A.