1.A.5: When identifying project constraints, which of the following is not true?

PrepAway - Latest Free Exam Questions & Answers

A.
TOGAF allows project architects to set aside principles that they believe would interfere with
the project as long as the decision to do so is explictly documented

B.
Enterprise wide constraints are often derived from the organization’s business and architecture
principles

C.
Project specific constraints should not supercede enterprise wide constraints.

D.
Specific technology solutions are not considered constraints when formulating the architecture
vision.

E.
Time, schedule, and resource availability are considered project constraints when formulating
the architecture vision.