1.H.3: In Phase H – Architecture Change Management, which of the following is most likely to be
resolved through a change management update?

A.
Re-architecting change
B.
Incremental change
C.
Simplification change
D.
All of these can be resolved through change management updates
E.
None of these can be resolved through change management updates