According to TOGAF, Which of the following activities is described as part of the approach in the Preliminary Phase of the ADM?
A.
Creating the Architecture Vision deliverable
B.
Defining a set of Architecture Principles
C.
Developing an Architecture Contract
D.
Extending the business scenario with business modeling
E.
Preparing a consolidated Gap Analysis