1.CA.3: In TOGAF, if a stakeholder’s concerns cannot be addressed in the proposed architecture
model, what is the proper response?

A.
If only one stakeholder is impacted, then eliminate those concerns and their related
requirements from the current ADM iteration.

B.
Revise the architecture vision for this ADM iteration.

C.
Create new models that cover the stakeholder’s concerns.

D.
Seek a dispensation from the Architecture Governance Board

E.
Create new models and viewpoints that cover the stakeholder’s concerns.