PrepAway - Latest Free Exam Questions & Answers

Which proposal should they use?

A customer is implementing a disaster recovery plan to backup data to a remote location 200
kilometersfrom their production facility. Which proposal should they use?

PrepAway - Latest Free Exam Questions & Answers

A.
Synchronously replicate data between the two sites using DWDM.

B.
Asynchronously replicate data between the two sites using DWDM.

C.
Synchronously replicate data between the two sites using a completelyfibre solution.

D.
Asynchronously replicate data between the two sites using a completelyfibre solution.


Leave a Reply