A customer has created a disaster recovery (DR) plan and is synchronously replicating its data to
a remote facility. The remote storage/server needs to be configured (LUN masking, zoning, and
rescanning the SCSI bus). To failover the application, what must the customer do?

A.
Failover storage, re-configure the remote storage/server, start application
B.
Failover storage, start application,re-configure the remote storage/server
C.
Pre-configure the remote storage/server, failover storage, start application
D.
Pre-configure the remote storage/server, start application, failover storage
Correct answer is C