PrepAway - Latest Free Exam Questions & Answers

What information must be gathered during the testing phase BEFORE allowing live customer data on the storage i

What information must be gathered during the testing phase BEFORE allowing live customer data
on the storage infrastructure? (Choose two)

PrepAway - Latest Free Exam Questions & Answers

A.
Time to failover, both without and with simulated load.

B.
Single points of failure in the infrastructure as well as topology mapping

C.
Hardware and software vendor escalation process including phone-home and /or
ticketgeneration.

D.
Powerup order, how long from power application to functionality per component, including dependencies.