Which product summarizes progress and is used to decide whether to amend the project scope or stop t

Which product summarizes progress and is used to decide whether to amend the project
scope or stop the project?

A.
End Stage Report

B.
End Project Report

C.
Checkpoint Report

D.
Product Status Account