What process is used by the Project Manager to maintain focus on delivery of a stage’s product

What process is used by the Project Manager to maintain focus on delivery of a stage’s
products within agreed tolerances?

A.
Managing Product Delivery

B.
Managing a Stage Boundary

C.
Directing a Project

D.
Controlling a Stage