which need to be managed after the project has closed? seenagape 10 years ago Which should be used to document any uncompleted work that needs to be done, and any riskswhich need to be managed after the project has closed? A.Follow-on action recommendations B.Exception Report C.Issue Register D.Risk Register ← Previous question Next question →