PRINCE2 Exam Questions

Which is an objective of the Closing a Project process?

Which is an objective of the Closing a Project process?

A.
Provision has been made to address any open issues or risks with follow-on action
recommendations

B.
Request authorization to start the next stage

C.
Prepare an Exception Plan as directed by the Project Board

D.
Ensure that the planned products are delivered to expectations and within tolerance