What process is used by the Project Board to respond to an Exception Report? seenagape 9 years ago What process is used by the Project Board to respond to an Exception Report? A. Controlling a Stage B. Managing a Stage Boundary C. Managing Product Delivery D. Directing a Project ← Previous question Next question →