When are tolerances for a Work Package agreed?

When are tolerances for a Work Package agreed?

A.
As work on each product within the Work Package begins

B.
Once ail products have been developed and approved

C.
When accepting a Work Package

D.
When the Stage Plan is authorized by the Project Board