The Project Board will allocate tolerances [ ? seenagape 10 years ago Identify the missing words in the following sentence. The Project Board will allocate tolerances [ ? ]to the Project Manager. A.for each Work Package B.for the project C.for each management stage D.for each technical stage ← Previous question Next question →