Which of the following are uses of the Risk Register during the Controlling a Stage process?

Which of the following are uses of the Risk Register during the Controlling a Stage process?
1. Obtain details on risks to include in a Highlight Report
2. Obtain details of risks that may affect the Stage Plan for the next stage
3. Capture uncertainties identified when authorizing a Work Package
4. Obtain details of any potential impacts that may affect the Business Case while reviewing the
stage status