Which of the following statements describes a risk event?
Which of the following statements describes a risk event?
which are they?
PRINCE2 proposes 3 levels of Plan, which are they?
Which of the following statements describes a risk effect?
Which of the following statements describes a risk effect?
which order should the next steps take place to produce a plan?
Having completed designing the plan, in which order should the next steps take place to produce a
plan?
1. Prepare Estimates
2. Define and analyze Products
3. Prepare the schedule
4. Identify activities and dependencies
What is the purpose of the Risk Management Strategy?
What is the purpose of the Risk Management Strategy?
Creating a Product sequence
Product based planning focuses on which of the following:
1. Creating product descriptions
2. Identifying activities
3. Creating a Product hierarchy
4. Creating a Product sequence
Which of the following risk responses can be used to seize an opportunity to ensure a risk ‘will’
Which of the following risk responses can be used to seize an opportunity to ensure a risk ‘will’
happen and the impact ‘will’ be realized?
Which of the following products is used after the Starting Up a Project process to capture and maintain inform
Which of the following products is used after the Starting Up a Project process to capture and
maintain information on all of the identified threats and opportunities relating to the project?
Who sets the tolerances for a work package?
Who sets the tolerances for a work package?
What is the name given to an individual who is responsible for the management, monitoring and control of all a
What is the name given to an individual who is responsible for the management, monitoring and
control of all aspects of a particular risk assigned to them?