Which is a correctly defined acceptance criterion for the transferred staff?
Additional Information
Product Description
Quality notes from the Daily Log
The Director of Information Technology Division (DIT) has been asked to ensure that any changes
to the outsourced staff employment contracts adhere to employment law. The DIT will review
future job descriptions of the transferred staff before the final contract is signed with the selected
service provider.
The service level agreement between MFH and the selected service provider will specify the type
and quality of service required. The selected service provider must follow the industry standards
for providing outsourced services.
MFH has a quality management system which contains a document control procedure for all its
documentation, however this does not include change management.
All project documents will be subject to a quality review. Nominated products will require a formal
approval record signed-off by the quality review chair.
Extract from the draft Quality Management Strategy (may contain errors)
Introduction
1. This document defines the approach to be taken to achieve the required quality levels during
the project.
2. The Project Board will have overall responsibility for the Quality Management Strategy.
3. Project Assurance will provide assurance on the implementation of the Quality Management
Strategy.
Quality management procedure – Quality standards
4. The selected service provider will operate to industry standards for providing outsourced
services.
5. MFH document standards will be used.
Records
6. A Quality Register will be maintained to record the planned quality events and the actual results
from the quality activities.
7. Configuration Item Records will be maintained for each product to describe its status, version
and variant.
8. Approval records for products that require them will be stored in the quality database.
Roles and responsibilities
9. The DIT will check that the employment contracts for outsourced staff adhere to employment
law.
10. Team Managers will provide details of quality checks that have been carried out.
11. Team Managers will ensure that the Quality Register is updated with the names of team
members who are involved in the review process.
12. The Senior User will review the Product Descriptions of the products to be produced by the
selected service provider to ensure that they can be achieved.
Which is a correctly defined acceptance criterion for the transferred staff?
A risk consists of a combination of the of a perceived threat or opportunity occurring and the magnitude of it
Identify the missing word in the following sentence… A risk consists of a combination of the of a
perceived threat or opportunity occurring and the magnitude of its impact on objectives.
Which is a correctly defined acceptance criterion for the running cost of the outsourced service?
Additional Information
Product Description
Quality notes from the Daily Log
The Director of Information Technology Division (DIT) has been asked to ensure that any changes
to the outsourced staff employment contracts adhere to employment law. The DIT will review
future job descriptions of the transferred staff before the final contract is signed with the selected
service provider.
The service level agreement between MFH and the selected service provider will specify the type
and quality of service required. The selected service provider must follow the industry standards
for providing outsourced services.
MFH has a quality management system which contains a document control procedure for all its
documentation, however this does not include change management.
All project documents will be subject to a quality review. Nominated products will require a formal
approval record signed-off by the quality review chair.
Extract from the draft Quality Management Strategy (may contain errors)
Introduction
1. This document defines the approach to be taken to achieve the required quality levels during
the project.
2. The Project Board will have overall responsibility for the Quality Management Strategy.
3. Project Assurance will provide assurance on the implementation of the Quality Management
Strategy.
Quality management procedure – Quality standards
4. The selected service provider will operate to industry standards for providing outsourced
services.
5. MFH document standards will be used.
Records
6. A Quality Register will be maintained to record the planned quality events and the actual results
from the quality activities.
7. Configuration Item Records will be maintained for each product to describe its status, version
and variant.
8. Approval records for products that require them will be stored in the quality database.
Roles and responsibilities
9. The DIT will check that the employment contracts for outsourced staff adhere to employment
law.
10. Team Managers will provide details of quality checks that have been carried out.
11. Team Managers will ensure that the Quality Register is updated with the names of team
members who are involved in the review process.
12. The Senior User will review the Product Descriptions of the products to be produced by the
selected service provider to ensure that they can be achieved.
Which is a correctly defined acceptance criterion for the running cost of the outsourced service?
What is the goal of the ‘identify context’ step as part of the risk management procedure?
What is the goal of the ‘identify context’ step as part of the risk management procedure?
Although it is not specified in the current corporate branding standards, the MFH corporate logo should be sho
Additional Information
Product Description
Quality notes from the Daily Log
The Director of Information Technology Division (DIT) has been asked to ensure that any changes
to the outsourced staff employment contracts adhere to employment law. The DIT will review
future job descriptions of the transferred staff before the final contract is signed with the selected
service provider.
The service level agreement between MFH and the selected service provider will specify the type
and quality of service required. The selected service provider must follow the industry standards
for providing outsourced services.
MFH has a quality management system which contains a document control procedure for all its
documentation, however this does not include change management.
All project documents will be subject to a quality review. Nominated products will require a formal
approval record signed-off by the quality review chair.
Extract from the draft Quality Management Strategy (may contain errors)
Introduction
1. This document defines the approach to be taken to achieve the required quality levels during
the project.
2. The Project Board will have overall responsibility for the Quality Management Strategy.
3. Project Assurance will provide assurance on the implementation of the Quality Management
Strategy.
Quality management procedure – Quality standards
4. The selected service provider will operate to industry standards for providing outsourced
services.
5. MFH document standards will be used.
Records
6. A Quality Register will be maintained to record the planned quality events and the actual results
from the quality activities.
7. Configuration Item Records will be maintained for each product to describe its status, version
and variant.
8. Approval records for products that require them will be stored in the quality database.
Roles and responsibilities
9. The DIT will check that the employment contracts for outsourced staff adhere to employment
law.
10. Team Managers will provide details of quality checks that have been carried out.
11. Team Managers will ensure that the Quality Register is updated with the names of team
members who are involved in the review process.
12. The Senior User will review the Product Descriptions of the products to be produced by the
selected service provider to ensure that they can be achieved.
Although it is not specified in the current corporate branding standards, the MFH corporate logo
should be shown on the front page of the service level agreement.
Which statement best describes the responsibilities of a risk actionee?
Which statement best describes the responsibilities of a risk actionee?
The service level agreement looks like any other MFH document.
Additional Information
Product Description
Quality notes from the Daily Log
The Director of Information Technology Division (DIT) has been asked to ensure that any changes
to the outsourced staff employment contracts adhere to employment law. The DIT will review
future job descriptions of the transferred staff before the final contract is signed with the selected
service provider.
The service level agreement between MFH and the selected service provider will specify the type
and quality of service required. The selected service provider must follow the industry standards
for providing outsourced services.
MFH has a quality management system which contains a document control procedure for all its
documentation, however this does not include change management.
All project documents will be subject to a quality review. Nominated products will require a formal
approval record signed-off by the quality review chair.
Extract from the draft Quality Management Strategy (may contain errors)
Introduction
1. This document defines the approach to be taken to achieve the required quality levels during
the project.
2. The Project Board will have overall responsibility for the Quality Management Strategy.
3. Project Assurance will provide assurance on the implementation of the Quality Management
Strategy.
Quality management procedure – Quality standards
4. The selected service provider will operate to industry standards for providing outsourced
services.
5. MFH document standards will be used.
Records
6. A Quality Register will be maintained to record the planned quality events and the actual results
from the quality activities.
7. Configuration Item Records will be maintained for each product to describe its status, version
and variant.
8. Approval records for products that require them will be stored in the quality database.
Roles and responsibilities
9. The DIT will check that the employment contracts for outsourced staff adhere to employment
law.
10. Team Managers will provide details of quality checks that have been carried out.
11. Team Managers will ensure that the Quality Register is updated with the names of team
members who are involved in the review process.
12. The Senior User will review the Product Descriptions of the products to be produced by the
selected service provider to ensure that they can be achieved.
The service level agreement looks like any other MFH document.
Which is NOT a recommended response type to respond to a threat?
Which is NOT a recommended response type to respond to a threat?
None of the reviewers have proof-reading skills.
Additional Information
Product Description
Quality notes from the Daily Log
The Director of Information Technology Division (DIT) has been asked to ensure that any changes
to the outsourced staff employment contracts adhere to employment law. The DIT will review
future job descriptions of the transferred staff before the final contract is signed with the selected
service provider.
The service level agreement between MFH and the selected service provider will specify the type
and quality of service required. The selected service provider must follow the industry standards
for providing outsourced services.
MFH has a quality management system which contains a document control procedure for all its
documentation, however this does not include change management.
All project documents will be subject to a quality review. Nominated products will require a formal
approval record signed-off by the quality review chair.
Extract from the draft Quality Management Strategy (may contain errors)
Introduction
1. This document defines the approach to be taken to achieve the required quality levels during
the project.
2. The Project Board will have overall responsibility for the Quality Management Strategy.
3. Project Assurance will provide assurance on the implementation of the Quality Management
Strategy.
Quality management procedure – Quality standards
4. The selected service provider will operate to industry standards for providing outsourced
services.
5. MFH document standards will be used.
Records
6. A Quality Register will be maintained to record the planned quality events and the actual results
from the quality activities.
7. Configuration Item Records will be maintained for each product to describe its status, version
and variant.
8. Approval records for products that require them will be stored in the quality database.
Roles and responsibilities
9. The DIT will check that the employment contracts for outsourced staff adhere to employment
law.
10. Team Managers will provide details of quality checks that have been carried out.
11. Team Managers will ensure that the Quality Register is updated with the names of team
members who are involved in the review process.
12. The Senior User will review the Product Descriptions of the products to be produced by the
selected service provider to ensure that they can be achieved.
None of the reviewers have proof-reading skills.
Which of the following Plans are approved by the Project Manager?
Which of the following Plans are approved by the Project Manager?