You need to prepare the infrastructure for the planned …

Your network contains a System Center 2012 Virtual Machine Manager (VMM) infrastructure.
The infrastructure contains 50 Hyper-V hosts.You plan to deploy Power Optimization for VMM.
You need to prepare the infrastructure for the planned deployment.
What should you do?
(Each correct answer present part of the solution. Chose two.)

PrepAway - Latest Free Exam Questions & Answers

A.
Install a Baseboard Management Controller (BMC) on each Hyper-V host.

B.
Enable Dynamic Optimization.

C.
Enable Hibernation.

D.
Enable Performance and Resource Optimization (PRO).

E.
Install a configuration provider on each Hyper-V host.

Explanation:
A: To use Power Optimization, the host computers must have a BMC that enables out-of- band management.
B: Power Optimization is an optional feature of Dynamic Optimization, and it is only available when a host group is configured to migrate virtual machines through
Dynamic Optimization.
Configuring Dynamic Optimization and Power Optimization in VMM
Dynamic Optimization – Balance the virtualmachine load among the Hyper-V servers in a Cluster.
Performance and Resource Optimization (PRO) – TIPS from SCOM used to optimize SCVMM
Placement Rules – Placement of virtualmachines on Hyper-V hosts based on rules, must, should etc