You need to move your task to match the deliverable finish date

In Microsoft Office Project Professional 2007, you have a project plan that has a task linked to a deliverable in another project. The Gantt chart shows that the other project deliverable finish date is a week in the future. You need to move your task to match the deliverable finish date. What should you do?

A.
In the Dependency pane, select Get Updates.

B.
In the Dependency pane, select Accept Changes from the Server for the appropriate deliverable.

C.
Set a deadline on the task.

D.
Update the Start date of the task.