Which three actions should you perform in sequence?

You are a SharePoint architect for Contoso, Ltd. Contoso has a SharePoint 2010 farm that contains four site
collections. Three site collections are available only inside the company network. The fourth site collection is
available to an external partner company by using forms-based authentication. The external site collection is
used to store contracts and purchase orders. Every site collection has its own content database.
Contoso purchases an Office 365 subscription for external partner employees. Contoso plans to move the
external site collection to SharePoint Online.
You have the following requirements:
Upgrade the external partner site collection to SharePoint Online.
Upgrade the on-premises farm to SharePoint 2013.
Minimize downtime for the upgrade.
Ensure the sites are read-only during the upgrade.
You need to plan the upgrade for the extranet site. Which three actions should you perform in sequence? To
answer, move the appropriate actions from the list of actions to the answer area and arrange them in the
correct order.Select and Place: