Microsoft Exam Questions

Which of the following is used only for the resource management reports in Microsoft Project Server?

Which of the following is used only for the resource management reports in Microsoft Project
Server?

A.
Base capacity

B.
Effort

C.
Remaining Availability

D.
Actual Capacity

Explanation: