Which of the following actions should you take?

You work as a developer at ABC.com. The ABC.com network consists of a single domain named
ABC.com.
ABC.com has a database, whose log file has reached capacity. You are instructed to make sure
that the database is able to successfully conclude transactions without having an effect on the
chain of log sequence numbers (LSNs).

Which of the following actions should you take?

PrepAway - Latest Free Exam Questions & Answers

A.
You should consider executing a full file backup.

B.
You should consider backing up the transaction log.

C.
You should consider executing a full database backup.

D.
You should consider executing a tail-log backup.

Explanation: