Which command should you use? seenagape 13 years ago You use bottom-up scheduling. You need to group four consecutive tasks in a major phase. You highlight the four tasks. Which command should you use? A.Outdent B.Fill Down C.Insert Summary D.Move Task ← Previous question Next question →