What option is a TRUE statement with regards to this process?

You are employed as an administrator at ABC.com. ABC.com makes use of Microsoft Dynamics
AX 2012 in their production environment.

You have created a Lean Manufacturing production flow model, and must now calculate the
Kanban quantities that are used in Kanban rules.
What option is a TRUE statement with regards to this process?

PrepAway - Latest Free Exam Questions & Answers

A.
After creating the Kanban quantity calculation, you first have to specify the date parameters
used in the calculation.

B.
After creating the Kanban quantity calculation, you first have to manually add calculation lines.

C.
After creating the Kanban quantity calculation, you first have to calculate the Kanban quantities
for each proposal line.

D.
After creating the Kanban quantity calculation, you first have to generate calculation lines that
are replenished by the associated Kanban rules.

Explanation: