PrepAway - Latest Free Exam Questions & Answers

The director of IT services identifies the following requirements for the planned deployment:

HOTSPOT
You plan to deploy a SharePoint Server 2013 server farm.
The president of your company sends you the following email message regarding the planned
deployment: ‘Our company loses an average of $5,000 per minute during service outages. At that
rate, $300,000 per hour is a major cost to the company and should be reduced or eliminated. The
company must provide continuity for IT services.”
The director of IT services sends you the following email message regarding the planned
deployment: The company plans to implement the following as part of the deployment:
Load balance all of the Web servers.
Perform daily and hourly backups of all data.
Centralize all of the service applications on a single server.
Provide redundancy for all of the network components, such as switches and routers.”
The director of IT services identifies the following requirements for the planned deployment:
Four front-end Web servers
One database server that will host all of the farm databases and will be replicated to another
database server by using log shipping
One dedicated application server that will host all of the service applications, including the Search
Service Application and all of the search components.
Select Yes if the statement can be shown to be true based on the available information; otherwise
select No.

PrepAway - Latest Free Exam Questions & Answers

Answer:

2 Comments on “The director of IT services identifies the following requirements for the planned deployment:


Leave a Reply