PrepAway - Latest Free Exam Questions & Answers

Tag: Exam 74-344

Exam 74-344: Managing Programs and Projects with Project Server 2013

You need to remove the resource demand from the resource plan

You are a project manager for an organization that uses Project Online.
You create a resource plan to provide high level resource demand during the portfolio intake and
selection process.

Your project is now selected for detailed planning. You complete a detailed work breakdown
structure (WBS).
You need to remove the resource demand from the resource plan.
What should you do?

You need to configure your resources to enable this method of assigning tasks

You are a project manager who uses Project Server 2013 and Project Professional 2013. You build a
project with common tasks for which many resources on your team can be used.
Because your resources have responsibilities outside of the project, you would like to have them
assign themselves to tasks they are able to complete.
You need to configure your resources to enable this method of assigning tasks.
What should you do?

You need to determine if a team member has available capacity to assist on another project or if this team mem

You are a project manager for an organization that uses Project Server 2013.
You are evaluating resource information in the Resource Center. The following information is
presented to you on the Resource Availability page:

You need to determine if a team member has available capacity to assist on another project or if this
team member is overallocated.
What should you do?

You need to allow project managers to plan workload and cost from the task level up

You are a Project Server 2013 administrator, and you support the Project Management Office (PMO)
project managers who need to estimate project hours and costs without knowing the specific
resource names.
There are options available to accommodate this request when creating resources on Project Server
2013.
You need to allow project managers to plan workload and cost from the task level up.
What should you do?

You need to include the change request in your baseline to see the impact of your overall project schedule inc

You are a project manager who uses Project Server 2013 and Project Professional 2013.
You are managing a project that has already begun. A new change request has been pre-approved,
and the director wants to understand the impact to the overall project schedule prior to formally
approving the project to include in the project schedule.
You add the change request to your project schedule. Your original baseline is Baseline1.
You need to include the change request in your baseline to see the impact of your overall project
schedule including duration, work, and cost.
What should you do?

Which two actions should you perform?

You work in an organization that uses Project Online. Project managers have full control over
resource assignments.
You work in the Project Management Office (PMO) and discover that two of your critical resources
are overallocated in the Resource Center for future work. They are critical resources because they
have specialized skills that no one else in your organization has, and they are integral to several
projects.
You need to determine how to correct the overallocation of these resources.
Which two actions should you perform? (Each correct answer presents part of the solution. Choose
two.)


Page 6 of 10« First...45678...Last »