You need to copy the custom fields from your customer’s project into your own

You are a project manager who uses Project Professional 2013. A customer has sent you a project
plan, which contains several custom fields that you want to use in your project. You have a custom
field named CF1 in the Number1 field in your project, and you have a custom field named CF2 in the
Number1 field of your customer’s project. You need to copy the custom fields from your customer’s
project into your own. You do not want to overwrite your project custom field. You open both
projects. What should you do next?

You need to use the most efficient method to produce a new plan with tasks based upon the old project plan

You are using Microsoft Project Professional 2013. Three years ago, you successfully completed a
project to review all of the suppliers within your organization, and you have been asked to run a
similar project again. You still have the project plan from three years ago. You need to use the most
efficient method to produce a new plan with tasks based upon the old project plan. What should you
do?

You need to update the actual work and mark the task complete

You are a project manager who uses Project Standard 2013. You manage a large project and are
capturing actual work for the tasks as they are being worked. You do not need to enter the time on
the actual day worked; however, you need to capture the total amount of time spent on the task.
The fixed work task has a baseline of 20 hours, and the developer’s timecard displays the following
hours:
Monday = 2 hours
Tuesday = 8 hours
Wednesday = 4 hours
Thursday = 2 hours
Friday = 2 hours
The developer informs you that the task is now complete.
You need to update the actual work and mark the task complete.
What should you do?