You need to achieve this goal using a custom field
You are using Project Standard 2013. You want the ability to see only tasks that have finish dates
past their deadline date You need to achieve this goal using a custom field. What should you do?
You need to correctly assign the resource
You are a project manager who uses Project Standard 2013. Your current project has resources with
the standard calendar as the base calendar. Some tasks of the project need to be done overnight so
the night shift calendar is assigned to those tasks. When you assign a resource to one of these tasks,
you get an error. You need to correctly assign the resource. What should you do?
You need to assign the weekend working calendar to the task
You are a project manager who uses Project Professional 2013. You are planning an office move,
which will occur over a weekend. You use Auto Scheduled tasks and create a weekend working
calendar. You need to assign the weekend working calendar to the task. What should you do?
You need to create a project file that contains this task list, ensuring that any fields are mapped correctly
You are a project manager who uses Project Standard 2013. A colleague sends you a Microsoft Excel
file that contains a list of tasks that define a project you must complete. You need to create a project
file that contains this task list, ensuring that any fields are mapped correctly. What should you do?
You need to copy the custom fields from your customer’s project into your own
You are a project manager who uses Project Professional 2013. A customer has sent you a project
plan, which contains several custom fields that you want to use in your project. You have a custom
field named CF1 in the Number1 field in your project, and you have a custom field named CF2 in the
Number1 field of your customer’s project. You need to copy the custom fields from your customer’s
project into your own. You do not want to overwrite your project custom field. You open both
projects. What should you do next?
You need to change the default for all new projects so that tasks will be created in Auto Scheduled mode
You are a project manager who uses Project Professional 2013. You need to change the default for
all new projects so that tasks will be created in Auto Scheduled mode. What should you do?
You need to use the most efficient method to produce a new plan with tasks based upon the old project plan
You are using Microsoft Project Professional 2013. Three years ago, you successfully completed a
project to review all of the suppliers within your organization, and you have been asked to run a
similar project again. You still have the project plan from three years ago. You need to use the most
efficient method to produce a new plan with tasks based upon the old project plan. What should you
do?
What are two ways to achieve this goal?
You are a project manager who uses Project Standard 2013. You regularly customize the Bar Styles
for a project prior to printing the project schedule. You need to add the Bar Styles button to the
Quick Access Toolbar as quickly as possible. What are two ways to achieve this goal? (Each correct
answer presents a complete solution. Choose two.)
You need to update the actual work and mark the task complete
You are a project manager who uses Project Standard 2013. You manage a large project and are
capturing actual work for the tasks as they are being worked. You do not need to enter the time on
the actual day worked; however, you need to capture the total amount of time spent on the task.
The fixed work task has a baseline of 20 hours, and the developer’s timecard displays the following
hours:
Monday = 2 hours
Tuesday = 8 hours
Wednesday = 4 hours
Thursday = 2 hours
Friday = 2 hours
The developer informs you that the task is now complete.
You need to update the actual work and mark the task complete.
What should you do?
You need to update the baseline for the new tasks
You are a project manager for a company that uses baselines in Project Standard 2013. Project
stakeholders approve an update to the baseline of a project in progress. You enter the new tasks
necessary to include the project schedule changes. You need to update the baseline for the new
tasks. What should you do?