Exam 70-633: TS: Microsoft Office Project Server 2007, Managing Projects

You need to modify the activity plan to accommodate the additional tasks and allow resources to continue to tr

You are managing an activity plan in Microsoft Office Project Server 2007.
You identify additional tasks with complex dependencies and multiple resources per task. You need to modify the activity plan to accommodate the additional tasks and allow resources to continue to track their work by using timesheets. What should you do?

you need to reduce resource availability to account for the sales support tasks

Over the next fiscal quarter, several resources will spend 25 percent of their time on sales support work. You want to allocate this time, but you do not have a license for Microsoft Office Project Professional 2007. In Microsoft Office Project Server 2007, you need to reduce resource availability to account for the sales support tasks. What should you do?

you need to save a version of the file that allows the contractors to modify your plan prior to publishing it

A project plan is published in Microsoft Office Project Server 2007. The resources include contractors who do not have Project Server user accounts. In Microsoft Office Project Professional 2007, you need to save a version of the file that allows the contractors to modify your plan prior to publishing it. What should you do?

On what should you base the resource utilization?

You create a project plan with a resource plan in Microsoft Office Project Server 2007. You can estimate work of individual tasks in the current phase, but you cannot estimate work of individual tasks in the next phase. You do not want to create dummy tasks in the project plan to manage resource utilization. You need to calculate the resource utilization of your project resources based on work in the current phase and the next phase. On what should you base the resource utilization?

You need to check resource availability to ascertain how much free time the resources required for the new pro

You manage a portfolio of projects that are saved to Microsoft Office Project Server 2007. Your organization is evaluating whether to take on another project. A key factor in that decision is whether the necessary resources will be available during the next 3 months. Your organization’s resources include full-time and part-time regular employees and some contractors with variable schedules. You need to check resource availability to ascertain how much free time the resources required for the new project will have during the next 3 months. What should you do?