You need to select the appropriate tool(s) for managing the project
You manage a development team by using Microsoft Team Foundation Server (TFS) 2012. The development
team is made up of developers with specific skills.
The project you are developing has the following characteristics:
· Several external dependencies exist.
· Requirements are well defined and will not change. · If an external dependency on the critical path does not
meet a committed to deadline, the project will be impacted.
· The impact should be identified and measured.
You need to select the appropriate tool(s) for managing the project.
What should you do?
What are two possible development processes you could select to achieve this goal?
You manage a highly complex project by using Microsoft Visual Studio Team Foundation Server (TFS) 2012
for application lifecycle management (ALM).
The project has the following characteristics:
· The development team is multi-disciplined, executes all work that is required, and has a high degreeof
autonomy.
· A key stakeholder acts as product owner to create, prioritize, and manage dynamic product requirements.
· You plan and complete requirements in three week cycles. · You do not need to keep track of an audittrail.
You need to select a development process.
What are two possible development processes you could select to achieve this goal? (Each correct answer
presents a complete solution. Choose two.)
You need to ensure that the new teams minimize collisions and maximize release flexibility
You are a scrum master.
You are planning a large product development project that will involve more than 15 team members. You want
to divide the team members into multiple scrum teams.
You need to ensure that the new teams minimize collisions and maximize release flexibility.
What should you do?
You need to describe to the team how the word "done" relates to Scrum
A development team is attempting to use Scrum as its process framework. You join the team as the new
scrum master.
During a meeting, a developer states that his “taskis done”.
You need to describe to the team how the word “done” relates to Scrum.
What should you do?
You need to get feedback from your stakeholders to verify that your application meets their requirements befor
(DRAG&DROP)
You are developing a new application that contains complicated validation and transformation logic on data
pulled from three separate source systems.
You need to get feedback from your stakeholders to verify that your application meets their requirements
before any other development tasks have been started. You also need to ensure that this application subsystem is correct before any other dependent modulecan be developed.
What should you do? (To answer, move the five appropriate actions from the list of actions to the answer area
and arrange them in the correct order.)
Which two actions should you perform?
You are developing an application by using a team of developers and a team of testers. You have an
automated nightly build.
Currently, the testers take too long to test and the developers are closing a large number of bugs as “unable to
reproduce.”
You need to improve the test cycle time.
Which two actions should you perform? (Each correctanswer presents part of the solution.
Choose two.)
Which three key metrics should you measure?
Your development team uses Scrum as its process framework. You need to identify key metrics for measuring
the effectiveness of any process changes.
Which three key metrics should you measure? (Each correct answer presents a complete solution. Choose three.)
Which three actions should you perform?
You are a technical team lead. Your company networkincludes a Microsoft Visual Studio Team Foundation
Server (TFS) 2012 server.
You are assigned to work on a project with an internal development team and an off-site vendor who is new to
working with your company.
You need to ensure that the code delivered by the off-site vendor is of an acceptable quality, conforms to
standards, and does not affect production support.
Which three actions should you perform? (Each correct answer presents a complete solution. Choose three.)
Which three benefits should you recommend?
Your company is considering implementing an application lifecycle management (ALM) strategy.
You need to identify the return on investment (ROI)of implementing an ALM strategy.
Which three benefits should you recommend? (Each correct answer presents part of the solution. Choose three.)
Which two actions should you perform?
Business analysts in your organization create large, extremely detailed requirements specifications. Some
business analysts report that developers are not delivering according to specifications.
You need to improve requirements management and delivery.
Which two actions should you perform? (Each correctanswer present part of the solution.
Choose two.)