You need to ensure that Baselinez displays work hours in the new summary task
You add a new summary task and detailed tasks to an existing project. You save the
changes as Baseline2. You discover that Baseline2 only displays work hours for detailed
tasks. You need to ensure that Baselinez displays work hours in the new summary task.
What should you do?
You need to compare the total work of your project’s deliverables against the baseline work
You need to compare the total work of your project’s deliverables against the baseline work.
What should you do?
You need to create a project plan that accommodates the corporate holiday calendar
You need to create a project plan that accommodates the corporate holiday calendar. What
should you do?
You need to create a project plan in Project 2010 from a list of tasks in a Microsoft Access 2010 database
You need to create a project plan in Project 2010 from a list of tasks in a Microsoft Access
2010 database. What should you do?
You need to turn off the feature that triggers the dependency to be automatically added
Every time you create a new task within your project schedule, Project 2010 automatically
adds a dependency to the new task. You need to turn off the feature that triggers the
dependency to be automatically added. What should you do?