what will happen if you enter the name of the database to be used by Analysis Services that does not exist alr
You work as the Project Administrator for company.com Inc. You need to create and schedule a new
cube for your organization. While building the cube, what will happen if you enter the name of the
database to be used by Analysis Services that does not exist already?
What does this figure indicate?
You work as a Project Manager for Tech Perfect Inc. Several projects are running under your
supervision. Martha, a team leader of a project, informs you about the performance indexes of her
project. The schedule performance index (SPI) of her project is 0.835. What does this figure indicate?
What must you do before you begin to execute the project?
The project customer has just approved your project plan and given you permission to start the
project. As the project manager, you must provide status reports at the end of each week, which
must include the current project status of schedule and cost, and how those compare to the original
plan. What must you do before you begin to execute the project?
What does this figure depict?
You work as a Project Manager for Tech Media Inc. Several projects are running under your
supervision. Rick, team leader of a project, provides you performance indexes of his project. The cost
performance index (CPI) of his project is 1.135. What does this figure depict?
Which of the following actions will you perform to estimate the costs without assigning specific people to tas
You work as a Project Manager for BlueSoft Inc. You use Microsoft Office Project 2007 for
developing the project schedule. You are assigned the project of remodeling a home. Your project
will require electricians to work on multiple tasks. You have five electricians to work on your project,
but you are not sure who will be the best for a certain task. Which of the following actions will you
perform to estimate the costs without assigning specific people to tasks?
What attribute must you assign to this resource type?
You work as the Project Manager for company.com Inc. You are using Microsoft Project Web Access
to manage your project teams. You would like to create a resource that serves as a model resource
for an upcoming electric project. You want the resource to be a “dummy” resource that emulates
electricians in the project. You do not want the dummy resource tied to a real account.
What attribute must you assign to this resource type?
what other method to accomplish the task?
You work as the Project Manager for company.com Inc. You need to migrate from your current
Project Server version to Project Server 2010. Hence, you want to create a backup of the Project
Web Access databases. You can use the backup and restore operation through the SharePoint
Central Administration Web site or what other method to accomplish the task?
How does the Microsoft Project Server calculate slack when you have multiple projects linked together to a mas
How does the Microsoft Project Server calculate slack when you have multiple projects linked
together to a master project acting as a program?
Which of the following is the most likely cause of the problem?
Sam works as the Project Administrator for company.com Inc. He has created a security template for
the project team leaders group. The project manager asks Sam to change some values within the
security template for the project team leaders group. Sam agrees and makes the changes. The
project manager reports that the members of the project team leaders groups are not able to use
the new permissions added by Sam to the template. Which of the following is the most likely cause
of the problem?
which of the following steps should you take so that the project team members cannot update the tasks that hav
You work as a Project Manager of the HHN Project of company.com Inc. You are compiling a P&L
Statement for your project and you have asked all of the project team members to enter their time
through Project Center on any tasks they have finished. Now that you are ready to submit the time
for all of the reported tasks in the Project Center, which of the following steps should you take so
that the project team members cannot update the tasks that have been reported?