So what action should you perform?
You work as an IT professional in an international corporation named wiikigo. You are experienced in deploying operating system and applications images. And in the company, your major job is to deploy Windows Operating system and troubleshoot everyday issues. The company has computers in two time zones. The company decides to have all the client computers installed with Windows Vista with Service Pack 1 (SP1). Since you are the technical support, the company assigns this task to you. Windows Automated Installation Kit (Windows AIK) is installed by you. You must make sure that in the process of the deployment process, the appropriate time zone setting is configured on each client computer. Meanwhile, you must reduce the number of images of Windows Vista SP1 to the least. So what action should you perform?
You need to allow resources to give their assignments to other team members for this project but not for other
You are asked to create a project plan in Microsoft Office Project Server 2007. You need to allow resources to give their assignments to other team members for this project but not for other projects. What should you do?
You need to meet Jeff Prices requirement
You need to meet Jeff Prices requirement. What should you do?
You need to see the project start and finish dates and the task start and finish dates on the table side of th
You create tasks in a project plan in Microsoft Office Project Standard 2007. You need to see the project start and finish dates and the task start and finish dates on the table side of the Gantt Chart view. What should you do?
So what action should you perform to accomplish your task? (choose more than one)
You work as an IT professional in an international corporation named wiikigo. You are experienced in deploying operating system and applications images. And in the company, your major job is to deploy Windows Operating system and troubleshoot everyday issues. On the corporate network, you manage operating system deployments by using Microsoft System Center Configuration Manager 2007 and Microsoft Deployment Toolkit (MDT) 2008. A new network is configured by you. This network is separated from the corporate network. According to the company requirement, computers on the new network should be deployed with a Windows Vista image. So what action should you perform to accomplish your task? (choose more than one)
You need to prevent projects created with this template from affecting named resource assignments
You are creating a project plan template that can be used by others to forecast budget and resource requirements on upcoming projects. Projects created with this template will be published to Microsoft Office Project Server 2007. You need to prevent projects created with this template from affecting named resource assignments. What should you do?
Which view should you create?
You need to create a view that will indicate whether project managers are fulfilling the requirements for updating their projects. Which view should you create?
What should you do?
You work from 8:00 A M. to 4:00 P.M. When scheduling projects in Microsoft Office Project Standard 2007, you set the working time of the project accordingly. When you create a new task, Project shows the finish time as 9:00 A M. on the following day. You need the finish time of new tasks to default to 4:00 P.M. What should you do?
What should you do?
You work from 8:00 A M. to 4:00 P.M. When scheduling projects in Microsoft Office Project Standard 2007, you set the working time of the project accordingly. When you create a new task, Project shows the finish time as 9:00 A M. on the following day. You need the finish time of new tasks to default to 4:00 P.M. What should you do?
From the following four actions, which two should be utilized to achieve the goal? (Choose more than one
You work as an IT professional in an international corporation named Wiikigo. You are experienced in deploying operating system and applications images. And in the company, your major job is to deploy Windows Operating system and troubleshoot everyday issues. Your company deploys Windows Vista and Windows XP with Service Pack 2 (SP2) images to the client computers by utilizing Business Desktop Deployment (BDD) 2007. The company has BDD installed on a Windows XP SP2 computer, and the computer is named Client01. All client computers in the company are being upgraded to Windows Vista SP1. You plan to utilize BDD to have Windows Vista SP1 images deployed. But the deployment cannot be implemented successfully. You should be enabled to utilize an automated deployment method to deploy Windows Vista SP1 images. From the following four actions, which two should be utilized to achieve the goal? (Choose more than one.)