Which action should be performed to achieve the goal?

You work as an IT professional in an international corporation named Wiikigo. You are experienced in deploying operating system and applications images. And in the company, your major job is to deploy Windows Operating system and troubleshoot everyday issues. Your company deploys Microsoft Office 2007 to client computers by utilizing Microsoft System Center Configuration Manager 2007. The installation of Office 2007 should be customized to have the license key contained. The license key should be prevented from being stored in plain text. Which action should be performed to achieve the goal?

You need to increase the task duration to 4 days, and ensure that the effort associated with the task does not

You are managing a project schedule in Microsoft Office Project Standard 2007. You create a fixed units task with a duration of 2 days. You have not yet assigned resources to the task. You need to increase the task duration to 4 days, and ensure that the effort associated with the task does not change. What should you do?

So what action should you perform to accomplish your task? (choose more than one)

You work as an IT professional in an international corporation named wiikigo. You are experienced in deploying operating system and applications images. And in the company, your major job is to deploy Windows Operating system and troubleshoot everyday issues. On the corporate network, you manage operating system deployments by using Microsoft System Center Configuration Manager 2007 and Microsoft Deployment Toolkit (MDT) 2008. A new network is configured by you. This network is separated from the corporate network. According to the company requirement, computers on the new network should be deployed with a Windows Vista image. So what action should you perform to accomplish your task? (choose more than one)

Which action should be performed to finish the task?

You work as an IT professional in an international corporation named Wiikigo. You are experienced in deploying operating system and applications images. And in the company, your major job is to deploy Windows Operating system and troubleshoot everyday issues. Your company deploys client computer images by utilizing Microsoft Deployment Toolkit (MDT) 2008. You are utilizing Lite Touch Installation (LTI) to configure MDT to deploy an image. You should be enabled to create a task sequence so as to have a previously captured image deployed successfully. Which action should be performed to finish the task?