You need to link Task A and Task B so that they occur in sequence, with the start date for Task B 5 days after

You are working in Microsoft Office Project Professional 2007 on a project plan in which Task A and Task B are independent. However, Task B must start 5 days after Task A is completed. You need to link Task A and Task B so that they occur in sequence, with the start date for Task B 5 days after the finish date for Task A. What should you do?

Which action should be performed?

You work as an IT professional in an international corporation named Wiikigo. You are experienced in deploying operating system and applications images. And in the company, your major job is to deploy Windows Operating system and troubleshoot everyday issues. Your company deploys the 2007 Microsoft Office system to client computers by utilizing Microsoft System Center Configuration Manager 2007. The installation of Office 2007 should be customized. In addition, the Office security settings should be defined during the installation.
Which action should be performed?