You need to include the change request in your baseline to see the impact of your overall project schedule inc

You are a project manager who uses Project Server 2013 and Project Professional 2013.
You are managing a project that has already begun. A new change request has been pre-approved,
and the director wants to understand the impact to the overall project schedule prior to formally
approving the project to include in the project schedule.
You add the change request to your project schedule. Your original baseline is Baseline1.
You need to include the change request in your baseline to see the impact of your overall project
schedule including duration, work, and cost.
What should you do?

Which two actions should you perform?

You work in an organization that uses Project Online. Project managers have full control over
resource assignments.
You work in the Project Management Office (PMO) and discover that two of your critical resources
are overallocated in the Resource Center for future work. They are critical resources because they
have specialized skills that no one else in your organization has, and they are integral to several
projects.
You need to determine how to correct the overallocation of these resources.
Which two actions should you perform? (Each correct answer presents part of the solution. Choose
two.)

You need to load your project with your desired resources against tasks

You are a project manager who uses Project Server 2013.
You build a project plan with the required tasks and want to add your resources. You know which
resources you would like to include but are not sure if they will be approved for your project.
You cannot formally assign these resources to the project until it is approved.
You need to load your project with your desired resources against tasks.
What should you do?

You need to retain historical information for both completed and in-progress tasks but create a baseline that

You are a project manager for an organization that uses Project Server 2013. You have the
appropriate permissions to set all baselines. Your project experiences a scope change, which
requires you to add tasks to the end of the schedule.
You need to retain historical information for both completed and in-progress tasks but create a
baseline that includes the newly-selected tasks.

You check out your schedule in Project Web App (PWA) for editing and select the newly-added tasks.
What should you do next?

You need to solve the overallocation by adjusting the Scheduled Start for the resources on your tasks to when

You are a project manager in an organization that uses Project Online. Project managers have access
to Project Professional 2013 for schedule management.
You create a project schedule with resource assignments on Monday. No resources are
overallocated. However, on Tuesday, you open the same project schedule and discover on several of
your tasks that resources show as overallocated.
Your project has a lower priority than other projects in the organization.
You need to solve the overallocation by adjusting the Scheduled Start for the resources on your tasks
to when the resources are available.
What should you do?

You need to include all projects and resolve the overallocations in the most cost-effective way

An organization is performing a Portfolio Analysis with Project Server 2013 to determine the projects
that will be executed the next year. The company has the following base staff: one application
developer, one business analyst, one project administrator, and one trainer.
The Resource Analysis is shown the following exhibit. (Click the Exhibit button.)

You need to include all projects and resolve the overallocations in the most cost-effective way.
What should you do?